Here’s what we know about the waterline replacement project and how soon it will be complete, per the City of Dayton Construction Inspector overseeing SP waterline project:
- The work has been delayed due to supply chain issues (the shipment of new fire hydrants).
- After Johnson is complete (Morton to Wayne), work will begin sequentially on Bonner (Hickory to Oak), then James (Hickory to Johnson) and finally Bradford (James to Theobald).
- The entire project is scheduled to be completed by October 1, 2022.
- The City will alert neighbors as the work progresses.
We’ll do our best to post updates here.

Related posts
Liberty School coming to South Park’s SE edge
Liberty High School is getting a new $10 million home in the South Park neighborhood that will allow the school to offer significantly more career tech programs and serve more high school dropouts.
A new school facility is under construction at the northeast corner of Wayne Avenue and Wyoming Street, near Wendy’s and the Sunoco gas station.
Dayton may reduce speed limits in business districts, possibly including Third Street, Wayne and Salem avenues
Did you catch this article from the Dayton Daily News? Thank you to our Wayne Avenue Traffic Safety Coalition for their continued efforts on this issue!
Wayne Avenue Traffic Safety featured in ThinkTV piece
Our WATSC team scores more coverage – this time by ThinkTV – on it’s campaign to increase pedestrian safety and promote business in South Park