Here’s what we know about the waterline replacement project and how soon it will be complete, per the City of Dayton Construction Inspector overseeing SP waterline project:
- The work has been delayed due to supply chain issues (the shipment of new fire hydrants).
- After Johnson is complete (Morton to Wayne), work will begin sequentially on Bonner (Hickory to Oak), then James (Hickory to Johnson) and finally Bradford (James to Theobald).
- The entire project is scheduled to be completed by October 1, 2022.
- The City will alert neighbors as the work progresses.
We’ll do our best to post updates here.
Related posts
Wayne Avenue Traffic Safety Coalition gets results!
WATSC has been relentless in their months-long campaign for the creation of a safer stretch of Wayne Avenue through the busy, pedestrian-heavy South Park business district. The results: a completed ODOT study and a safer street design on the drawing board.
Year in Review: Our hard-working neighborhood improvement council accomplished plenty in 2024
From neighborhood safety, to playground improvements, to tackling nuisance properties and our usual social and volunteer activities, 2024 was another busy year for South Park.
The next phase of Flats at South Park construction to begin Spring 2025
More development coming to the west side of South Park. Phase 3 of the Flats at South Park construction project to being in Spring 2025.